• Development of a 60m wide, 76 km long city level Ring Road estimated cost of Rs.335crores
• Usually, the land acquisition process is used to acquire land for provision of infrastructure
• The land falling in urbanized zone, of 59 K.m. length, is procured through TP Scheme.
• Length of 17 k.m. falling in non urbanized area is acquired by land acquisition.
• Two lane road is operational and one BOT base construction of two lane is started and it is likely to be completed by June ‘08